1) Akao Cafe & Homestay, Chiang Rai: phase 2 · Off-grid

  • System: 16 kW off-grid solar with 48 kWh of battery storage (3 × IntelliHome 16 kWh batteries).
  • What it powers: the new building: four guest houses, a staff room, storage and a dedicated battery room. It runs as its own system, separate from the café's existing solar.
  • Why off-grid: the guest houses get clean power day and night, with no grid connection and no monthly electricity bill.
  • Where and when: Mae Suai Dam area, Mae Suai, Chiang Rai. Work started in November 2026.

2) M-Harmony Resort, Mae Khao Tom, Chiang Rai · Off-grid, three-phase

  • System: 50 kW three-phase hybrid inverter with 60 kWh high-voltage FlexCore battery storage, built to grow to about 100 kWh as guest numbers rise.
  • Panels: 45 × 650 W high-efficiency panels (about 29 kWp) on a galvanised steel ground mount set on screw piles: quick to build, no large concrete pours.
  • Back-up: a generator connected through an automatic transfer switch for long cloudy spells.
  • Where and when: Mae Khao Tom, Mueang Chiang Rai. Target: running by early December 2026.

3) Starbucks @ My Park, Chonburi · Commercial on-grid

  • System: 30 kW Huawei on-grid inverter with 48 × 670 W rooftop panels (about 32 kWp).
  • Our scope: installation, testing and commissioning under an EPC contract.
  • When: installation 11–24 November 2026 (14 days).
  • Insured: covered from the first day on site by our Contractor All Risk (CAR) insurance. More about this project →

Plan your own projectInstallers: open jobs

Ongoing project

Starbucks – My Park, Chonburi

A commercial on-grid rooftop solar system we are installing now, insured from the first day on site.

In progress · Nov 2026

On-grid rooftop PV, about 32 kWp

  • Panels: 48 × AIKO Comet 670 W
  • Inverter: Huawei SUN2000-30KTL (30 kW)
  • Installation: 11 – 24 November 2026 (14 days)
  • Our scope: installation, testing and commissioning under an EPC contract
  • Workmanship warranty: 2 years
  • Location: My Park, Chonburi
Insured · Contractor All Risk (CAR)

Protected by our CAR policy

  • Insurer: Dhipaya Insurance PCL
  • Policy period: 16 Oct 2026 – 16 Oct 2027, plus 12 months' maintenance cover per project
  • Contract works: all risks of physical loss or damage, up to 5,000,000 THB per contract
  • The owner's existing building: up to 1,000,000 THB per event
  • Third-party liability: up to 1,000,000 THB per event
  • Maintenance period: third-party cover continues for 12 months after handover

Cover is subject to the policy terms, conditions and exclusions. The certificate is furnished upon request. About our CAR insurance ↑

Your opinion

How likely are you to recommend Solar ESS to a friend or colleague?

1 = Not at all likely10 = Extremely likely

One score per month from each internet connection. Your IP address is never stored.

LINEFacebookCall us